1. On the 2nd or 3rd order day, kindly contact supplier whether they pass it to production department.
2. 7days later, ask them yarn is ready or not?
3. 5-7days later, when is weaving day on machine? How many days for weaving?
4. Next, when is ready scarf date?
5. When to start sewing label and packing?
If factory is not in peak season, above total lead time is around 30-35days.
In peak season, total time might get 50days.
So to make sure unexpected things not disrupt your plan,
Please insist on: order earlier, less cost.
1. On the 2nd or 3rd order day, kindly contact supplier whether they pass it to production department.
2. 7days later, ask them yarn is ready or not?
3. 5-7days later, when is weaving day on machine? How many days for weaving?
4. Next, when is ready scarf date?
5. When to start sewing label and packing?
If factory is not in peak season, above total lead time is around 30-35days.
In peak season, total time might get 50days.
So to make sure unexpected things not disrupt your plan,
Please insist on: order earlier, less cost.